From first principles to successful project delivery

Project value: £22m+
Sector: Highways and Public Realm
Services: Tender Programming | Early Contractor Involvement | Construction Planning | Progress Monitoring | Clause 31 and Clause 32 Programmes

The Challenge

The Sheffield Transforming Cities Fund (TCF) scheme aims to improve public transport, walking, wheeling and cycling infrastructure across the city.

Project Planning Ltd was approached to develop the tender programme with just six weeks until submission and no prior involvement in the scheme.

Although draft construction drawings were available, the design continued to evolve, requiring substantial elements of the initial planning work to be revisited as construction issue drawings became available.

The challenge was to produce a credible, deliverable programme within a demanding timescale while accommodating evolving design information and emerging traffic management requirements.

Our Approach

We developed the programme from first principles.

Our planners undertook planning take-offs, proposed realistic construction outputs for verification and buy-in from the site team, developed traffic management sequences and phasing proposals before building the programme in Primavera P6.

This practical, construction-led approach provided a robust foundation for both the tender submission and subsequent delivery.

During Early Contractor Involvement (ECI), we worked alongside the delivery team as the design developed.  Significant changes prompted collaborative workshops focused on value engineering, risk reduction and programme improvement.

We also identified opportunities to refine traffic management constraints and improve construction sequencing.

Supporting Construction Delivery

Our involvement continued into construction, with weekly site visits to capture progress, assess change and maintain an accurate forecast.

By combining site knowledge with programme analysis, we helped the delivery team identify recovery opportunities and demonstrate the effects of design changes and unforeseen site conditions.

We also employed earned value techniques to provide an objective indication of progress against the planned programme.

The Outcome

The project has achieved levels of reported performance that impressed the client sufficiently to prompt independent audits of the reporting.

The audits confirmed that the reported performance was accurate.

From an initial six-week tender challenge through ECI and construction, Project Planning Ltd provided consistent, practical planning support that helped the delivery team understand progress, manage change and make informed decisions.

Good planning is more than producing a programme.  It is about communicating it, adapting it and helping projects succeed.